(This is the third of three posts from Sunday night)
I expect to get lots of progress this coming week:
> Pickup and install the wetbar counter in the family room
> Tile the new bathroom and the counters
> Install sinks in the new bathroom and the two wetbars
> Finish the access doors in the downstairs bedrooms and the master bedroom closet
> Mortise the new interior doors for hinges. Paint the doors, drill them for locks and handles, and hang them (sounds like a movie parody)
> Install the commodes
> Install the pedestal sink downstairs, once the workmen are done with cleaning their paint and mud brushes
> Figure out how to reinstall the heater covers (of all the tasks, this is the one I fear the most)
> Install the granite countertops in the kitchen and install the plumbing
> Get and install door handles for the four exterior doors
> Get power to the sprinker system (currently using an extension cord)
> Begin putting in the baseboard
> Chop down the ugly two trees in front
Obviously more than I can possibly do myself. Walter and his crew of professionals will be helping, as will Frank and John. I'm still eager to be finished on the 15th.
I'm still shooting for June 15 completion. It'll be tough, there's numerous tiny details still left.
Sunday, June 3, 2007
June 3
We made great progress last week and got the following accomplished:

> Painted the exterior body color in a cream/yellow shade. Began the secondary color (deep navy blue)
> Installed the master bath vanity and prepared the surface for tile
> Tore out the cast iron tub in the second upstairs bathroom. Only weighed about 250 pounds. Kathleen managed to get rid of it on Craig's List, so I didn't have to deal with taking it to the recycle place.
> Build plumbing in the upstairs second bathroom for the second sink. What a nightmare, I'm so glad Frank did the work.
> Installed all shower and tub faucets
> Installed and wired the recessed light cans in the master bedroom
> Got measured for carpet
> Repaired the fence gate
> Built the access for the sprinkler valves in the downstairs bathroom
> Drywalled the upstairs bathroom
Thursday, May 31, 2007
Back Steps
Frank and John came over last week to help me. I realized that I wasn't going to make the June 15 date unless I got some help, so the budget continues to go over...
Anyway, one of the things they did was build a new set of steps for the back patio. The old ones were pretty raunchy and narrow. And some former owner built some sort of windbreak from which to tend bar on the patio. All in all, a rather unappetizing sight from a re-sale perspective.
Pretty good job, eh?
Wednesday, May 30, 2007
Nemisis gone
The fireplace wall has been my nemesis, and my nemesis is
conquered.
Friday was a HUGE day: The painters painted the two walls, and you can't even tell how bad they once looked. What a relief, the ugly wall, my nemesis is no more.
For some reason, a previous owner had the lovely brick wall in the living and bedroom plastered. But left big holes in the Mexican Restaurant
look. I knew no potential buyer would want that, so I needed to fill them in. I spent hours and hours and hours patching the holes, 1/4 inch at a time. At the end I sanded the plaster, then put on more, then sanded, etc etc etc. I'd have white lung disease had I not been wearing my respirator.
Friday was a HUGE day: The painters painted the two walls, and you can't even tell how bad they once looked. What a relief, the ugly wall, my nemesis is no more.
Monday, May 28, 2007
Memorial Day
Spent a half day with Kathleen helping me. Last Friday I demolished the upstairs bathroom and re-wired the GFI outlet and moved the electrical connection for the lights. Oh, and I drilled the holes for the plumbing for the double vanity.
Today Kathleen cleaned up the master bedroom, master bath and downstairs north bedroom. Yech, what a job... they were filled with construction debris and dust. Lots of dust. Expecially in the carpets and pads which she removed.
Today I removed all the tile around the tub in the upstairs bathroom. And together we measured where to put the recessed lights in the master bedroom. I wanted to make sure we measured twice and cut once, as I don't get a second chance as everything has been painted.
The plan for this short week:
> Plumb the upstairs bath
> Sheetrock and mud the bathroom
> Install floor tile in the bathroom
> Install tub in the bathroom
> Install fixtures in the master and downstairs bathrooms
> Install the recessed lights for master bedroom
> Install kitchen cabinets
> Finish painting interior
> Select exterior color scheme
> Install range, microwave and dishwasher
> Install vanity in master bathroom
> Order carpet
Sounds like a bunch of work. I am shooting for completion on June 15, so I'm going to outsource more of the work to Frank.
Today Kathleen cleaned up the master bedroom, master bath and downstairs north bedroom. Yech, what a job... they were filled with construction debris and dust. Lots of dust. Expecially in the carpets and pads which she removed.
Today I removed all the tile around the tub in the upstairs bathroom. And together we measured where to put the recessed lights in the master bedroom. I wanted to make sure we measured twice and cut once, as I don't get a second chance as everything has been painted.
The plan for this short week:
> Plumb the upstairs bath
> Sheetrock and mud the bathroom
> Install floor tile in the bathroom
> Install tub in the bathroom
> Install fixtures in the master and downstairs bathrooms
> Install the recessed lights for master bedroom
> Install kitchen cabinets
> Finish painting interior
> Select exterior color scheme
> Install range, microwave and dishwasher
> Install vanity in master bathroom
> Order carpet
Sounds like a bunch of work. I am shooting for completion on June 15, so I'm going to outsource more of the work to Frank.
Monday, May 21, 2007
Boycot Homelite products
Two weeks ago I bought a Homelite brand electric lawn mower at Home Depot. Yesterday Kathleen hit a hidden root and bent the blade.
After hours at Home Depot and Lowes, came to discover that no aftermarket blades fit the Homelite mowers.
The Homelite website does not recognize the model number that I bought. Their "customer service" department is open 7 till 4 Eastern time, which kinda ignores 70% of their market. And when you finally do get through to them, they don't sell replacement blades.
I wish I had never bought that mower. Do yourself a favor and tell anyone who'll listen to avoid products from that company.
After hours at Home Depot and Lowes, came to discover that no aftermarket blades fit the Homelite mowers.
The Homelite website does not recognize the model number that I bought. Their "customer service" department is open 7 till 4 Eastern time, which kinda ignores 70% of their market. And when you finally do get through to them, they don't sell replacement blades.
I wish I had never bought that mower. Do yourself a favor and tell anyone who'll listen to avoid products from that company.
Mud
Today I worked on finishing up patching the ugly brick and plaster walls in the bedroom and living room. I carefully mixed the mud (drywall compound actually, everyone just calls it mud) using my hand held Oster mixer (worked great), applied it, and sanded it. Took hours and hours and hours.
At the end of the day the fellow who was applying paint texture to the walls couldn't stand it any more. He got out his mud knife and applied some to one of the holes. In two minutes he accomplished as much as would have taken me two hours.
He then proceeded to teach me how to do it. I'm now an expert, though next time I'll hire someone who has experience!
At the end of the day the fellow who was applying paint texture to the walls couldn't stand it any more. He got out his mud knife and applied some to one of the holes. In two minutes he accomplished as much as would have taken me two hours.
He then proceeded to teach me how to do it. I'm now an expert, though next time I'll hire someone who has experience!